xpsoccer.com.

Mt Stapylton – Commercial Storage Warehouse

//Mt Stapylton – Commercial Storage Warehouse
Project Details

Woolshed Road STAPYLTON

Client: Salmon Earthmoving

Date: 2008

Project Description

Description: 1 X large Wharehouse with internal panel wall 2 internal rooms

  • Tiltcon team worked closely with the architects and structural engineers, on site P&D foreman, local suppliers and subcontracts, to accomplish the 35 Panel building.
  • The project had 5 large casting beds, allowing to stack all the layers of panels, which was lifted by a 20t crane over 2 days.
  • Duration time was 2 weeks. (casting beds to Panel Lift)
  • Poured internal floor slab approx m3

Service provided:

  • casting beds
  • formwork
  • reo fixing
  • concrete place and finish
  • panel lifting
  • panel bracing
  • joint sealing
  • Earthworks